Salvage Operation

Bollard Salvage Completed in a Record 4 Hours at APM Terminals

Rock & Reef Dredging successfully completed the recovery of a fallen bollard at APM Terminals in a record time of just 4 hours, delivering a challenging salvage operation with precision and efficiency.

Using our advanced Liebherr crane system, expert operators, and a methodical grid-based dredging approach, we were able to locate and retrieve the bollard from beneath heavy siltation and zero-visibility conditions. Our four-point mooring setup ensured exceptional positional accuracy, while continuous load-variation monitoring allowed us to identify the submerged object quickly and safely.

This project demonstrates our ability to execute high-risk, time-critical marine operations with unmatched expertise, planning, and technical capability. Rock & Reef remains committed to providing reliable and efficient dredging and salvage services for ports and terminals across India.

 

whatsapp